We see the Activity Center to be a tool to reach out to the community so that people who are far from God may be drawn closer to Him in Christ Jesus.
Timeline of Planning Events:
March 2009: Congregation-wide focus groups
developed Activity
Center program of spaces.
Fall 2009: Architectural master plan and schematic
drawings for
Activity Center developed.
March 2010: Congregation voted to proceed with
Activity Center
building phase.
May 2010: Application submitted to Duke Endowment
for $150,000
rural church grant –application continues to be “in process” with an
anticipated approval date in 2012-2013.
Spring 2011: Capital Campaign begins.
Activity Center update April 27, 2011
Budget:
Loans for all previous building projects were paid in full as of December 2010.